Local Plan 2026-2046 Timetable

On 26 June 2026, the Local Plan Timetable came into force alongside the Notice of Commencement. Please note that this timetable may be updated to reflect progress with existing policy documents, subject to an updated evidence base and national policy. 

Cannock Chase Local Plan 2026 – 2046 TimetableDates

Stage 1: Scoping

Key Activities:

  • Publication of Notice of Intention to Commence the New Local Plan | Regulation 19
  • Initial evidence base review: Housing and Employment Needs, Flood Risk, Landscape Character etc.

Community Involvement:
Statutory Public Engagement: Scoping Consultation | Regulation 20

Spring – Autumn 2026

 

June/July 2026

 

 

August/September 2026

Gateway 1: Self Assessment | Start of the 30 month 
Local Plan Period | Regulation 21 
October 2026

Stage 1: Proposed Content of Plan and Supporting Evidence

Key Activities:

  • Early stage visioning and options
  • Vision and Strategic Options
  • Initial Evidence Base Review: IIA, SFRA, HIA, Green Belt Assessment Part 2 etc.)
  • Publication of summary of scoping consultation | Regulation 22

Community Engagement:
Statutory Public Engagement: Vision and Strategic Options | Regulation 23

November 2026 – June 2027

 

 

 

May – June 2027

Stage 2a: Draft Plan Preparation

Key Activities: 

  • Publication of summary of Vision and Strategic Options Consultation | Regulation 24
  • Site assessments
  • Strategic policy drafting
  • Prepare for Gateway 2
July – September 2027
Gateway 2: MHCLG review of Draft Plan | Regulation 26    October 2027

Stage 2b: Draft Plan Preparation

Key Activities:

  • Draft Local Plan
  • Draft Policies Map

Community Engagement:
Statutory Public Engagement: Proposed Draft Local Plan Consultation | Regulation 27

October 2027 – January 2028

 

 

February – March 2028
 

Stage 2c: Final Proposed Plan Preparation

Key Activities:

  • Publication of summary of Draft Local Plan Consultation | Regulation 30
  • Finalise submission documents
  • Prepare for Gateway 3
     

April – July 2028

 

 

 

Gateway 3: Submission of the Local Plan to the Secretary of State | Regulations 31 - 33July/August 2028

Stage 3: Submission and Examination

Key Activities:

  • Submit to the Planning Inspectorate (PINS) | Regulation 34
  • Publish Local Plan
  • Publish Policies Map
  • Publish Consultation Reports
  • Independent Examination | Regulation 35
  • Examination Hearings
  • Main Modifications (if required)
  • Consultation of Main Modifications (if required) 
  • Receipt of Inspector’s Final Report | Regulation 37

Community Involvement: 
Attend Examination hearings (public)
Representations of Main Modifications (if required)

 

October 2028 – March 2029

 

 

 

 

 

 

 

 

 

Stage 4: Adoption | Regulation 39

Key Activities:

  • Adoption by Full Council
  • Publication of Adoption Statement
  • Update Digital Local Plan
  • Begin monitoring cycle

Community Involvement:
Local Plan available for inspection
Community notified of adoption    
 

April 2029

 

 

 

 

 

 