On 26 June 2026, the Local Plan Timetable came into force alongside the Notice of Commencement. Please note that this timetable may be updated to reflect progress with existing policy documents, subject to an updated evidence base and national policy.
| Cannock Chase Local Plan 2026 – 2040 Timetable | Dates |
Stage 1: Scoping Key Activities:
Community Involvement: | Spring – Autumn 2026
26 June 2026
3 August - 14 September 2026 |
| Gateway 1: Self Assessment | Start of the 30 month Local Plan Period | Regulation 21 | October 2026 |
Stage 1: Proposed Content of Plan and Supporting Evidence Key Activities:
Community Engagement: | November 2026 – June 2027
May – June 2027 |
Stage 2a: Draft Plan Preparation Key Activities:
| July – September 2027 |
| Gateway 2: MHCLG review of Draft Plan | Regulation 26 | September - December 2027 |
Stage 2b: Draft Plan Preparation Key Activities:
Community Engagement: | December 2027 – March 2028
May – July 2028 |
Stage 2c: Final Proposed Plan Preparation Key Activities:
| July/August 2028
|
| Gateway 3: Submission of the Local Plan to the Secretary of State | Regulations 31 - 33 | July/August 2028 |
Stage 3: Submission and Examination Key Activities:
Community Involvement:
| October 2028 – March 2029
|
Stage 4: Adoption | Regulation 39 Key Activities:
Community Involvement: | April 2029
|